Current Tasks vs. All Tasks

M

Marc

On the Tasks page, what criteria needs to be met for a task to show in All
Tasks and what needs to be met in order to show in Current Tasks? Is it
simply that remaining work is equal to zero, or is there more to it than that?

Thanks!
 
E

Engelbert

You presumably mean what is in the English language version called "Active
Tasks". There is no "Current Tasks"

Whatever all you have to do is go to Modify Settings; Click on Active Tasks
and look at which filter is being used.

.... which should be Status is not equal to Completed

Engelbert
 
E

Engelbert

Sorry, I thought I was in the portal server newsgroup.

(I suppose it might apply to your version of Tasks though. Might)

Engelbert
 
G

Gérard Ducouret

Hello Marc,
AFAIK, "Current Tasks" are tasks with remaining work NOT equal to zero (even
tasks located in the past). For tasks positionned in the future you can set
a time limit :
In PWA (rough translation from French):
Admin / Customize PWA / Current task includes..... (at the bottom of the
page)

Hope this helps,

Gérard Ducouret
 
R

Reid McTaggart

Current tasks includes:
All task assignments from Administrative projects
All task assignments with remaining work
All task assignments scheduled to start within the next x days (x is defined
in the configuration settings)
 