Current vs All Tasks

J

jem

I have one PM using PWA that can not choose to view only Current Tasks. I
have checked the date ranges, and everything looks normal. He has tasks
that are due within the current two week period. I've even tried changing
the date range, but nothing seems to work. Any time he chooses 'Current
Tasks' it automatically jumps back to 'All Tasks'. Has anyone seen this
problem before, and/or know how to resolve it?

Thanks.
jem
 
D

Dee

I have seen that happen only when there are no tasks that start within
or are due within the number of days entered in the current tasks setup
in "Customize Project Web Access". Or maybe the tasks could have zero
remaining work??

HTH

-Dee
 
D

Dee

Ok, my co-worker seems to have found the solution to this.


1. close all IE windows.
2. Open IE and dump your cache: Tools->Internet Options->Delete
Files->Delete all offline content->OK.
3. plug in the url for Project server.

It worked for me!

Regards,
Dee
 