Custom begin and end columns

C

Carlos Marin

Hi,

I need to display a task's begin and end column using the local "time" format.
How can i do this?

Thanks in advance.
 
R

Rob Schneider

Carlos said:
Hi,

I need to display a task's begin and end column using the local "time" format.
How can i do this?

Thanks in advance.

I'm not sure what you mean by "begin" and "end". If you mean "Start" and
"Finish", then if these fields are not already shown in a column,
right mouse click on the headings of the columns and insert that field.
You'll notice here are other date fields available for your use. You
can learn more about each field if after the field is displayed in a
column, you hover the mouse pointer over the field name and then click
on the link to help. You can change the date/time format of date/time
fields in the Menu: Tools, Options, Tab: View.
 
J

JulieS

Hello Carlos,

You can add time to start and finish dates through Tools > Options,
View tab and select a format that shows date and time. It will show
the formats as set in the Regional settings.

I'm not sure what you mean by local time format.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 