R
Ryan
Hi All,
I have a task that can only be done on the 1st or 3rd Tuesday of every month
and I need to set up a custom calendar or something to limit it to this.
Here's a generic version of my tasks.
Task 1 - planning.
Task 2 - commission meeting (this is the task that only happens on the 1st
or 3rd tuesday)
Task 3 - construction.
So if planning (Task 1) goes past the 1st tuesday of the month, then task 2
needs to be pushed back to the 3rd tuesday of the month. Is there any way
to do this?
Thanks,
Ryan
I have a task that can only be done on the 1st or 3rd Tuesday of every month
and I need to set up a custom calendar or something to limit it to this.
Here's a generic version of my tasks.
Task 1 - planning.
Task 2 - commission meeting (this is the task that only happens on the 1st
or 3rd tuesday)
Task 3 - construction.
So if planning (Task 1) goes past the 1st tuesday of the month, then task 2
needs to be pushed back to the 3rd tuesday of the month. Is there any way
to do this?
Thanks,
Ryan