Custom Calendar not available

T

Terri

I am using MS Project 2003
I set up a "new" calendar with the Company's holidays. I do not want to
change the Standard calendar as procurement items are based on calendar days
not working days. When I started a new project, the "Company" calendar is
not available, only the three basic MS Project calendars are available. Do I
have to set up a company calendar every time I start a new project???

Thanks
 
D

Dale Howard [MVP]

Terri --

Open the project in which you created the new calendar and do the following:

1. Click Tools - Organizer.
2. Click the Calendars tab.
3. Select your custom calendar on the right side of the dialog.
4. Click the Copy button.
5. Click the Close button to close the dialog.

The above set of steps will copy the calendar to your Global.mpt file, which
makes it available to all current and future projects. Hope this helps.
 
T

Terri

Ahhh yes, now I remember, thanks a bunch.

Dale Howard said:
Terri --

Open the project in which you created the new calendar and do the following:

1. Click Tools - Organizer.
2. Click the Calendars tab.
3. Select your custom calendar on the right side of the dialog.
4. Click the Copy button.
5. Click the Close button to close the dialog.

The above set of steps will copy the calendar to your Global.mpt file, which
makes it available to all current and future projects. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top