T
Terri
I am using MS Project 2003
I set up a "new" calendar with the Company's holidays. I do not want to
change the Standard calendar as procurement items are based on calendar days
not working days. When I started a new project, the "Company" calendar is
not available, only the three basic MS Project calendars are available. Do I
have to set up a company calendar every time I start a new project???
Thanks
I set up a "new" calendar with the Company's holidays. I do not want to
change the Standard calendar as procurement items are based on calendar days
not working days. When I started a new project, the "Company" calendar is
not available, only the three basic MS Project calendars are available. Do I
have to set up a company calendar every time I start a new project???
Thanks