Hi,

I do have a challenge, and I am not sure how to face it.

AS per our financial calendar, each month ends the last friday of the month.

Also the fiscal Year starts the day following the last friday of october.

I would like to be able to see a calendar tah fits these rules.

For example June Starts MAY 26TH and ends JUNE 22ND !


Thanks,
Nde
 
J

John

Nde said:
Hi,

I do have a challenge, and I am not sure how to face it.

AS per our financial calendar, each month ends the last friday of the month.

Also the fiscal Year starts the day following the last friday of october.

I would like to be able to see a calendar tah fits these rules.

For example June Starts MAY 26TH and ends JUNE 22ND !


Thanks,
Nde

Nde,
Unfortunately Project does not support accounting month calendars. There
are a few options. First, you can manually copy the timescaled data to
Excel and then parse it out by accounting month, but this would be
really tedious and prone to errors. Second, you could write, or have
written, a VBA macro that does the export (I've done this twice myself).
This approach has the most flexibility and is very reliable. Third, I
recently saw a post on our developer newsgroup from a company
(forproject.com) that may be able to help.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top