J
James G
Let's see if anyone in the world can help me on this one!
I've been using MSP for several years now (currently on MSP 200)...and I
hope that I'll explain my predicament succinctly
I can set-up the calendars, Change Working Time, and custom calendars
without too much difficulty....and I fully understand (I think!) the settings
via Tools/Options/Calendar (TOC)..which sets the definition of how many hours
equals one working day.
The Problem: If I apply a custom task or resource calendar to that task,
then the start of the task amends in accordance with the custom calendar
(good!), but the duration (therefore the end-date) alters in accordance with
how many hours-per-day have been defined in the TOC settings, regardless of
the working-times set by the custom calendar. This results in an incorrect
number of hours work for the resource, unless I go into each task and amend
the work in accordance with the true working times of the resource.
The Example: The basic/project calendar has been set for 06:00 start: and
18:00 finish, with 12 Hrs-per-day. The basic resources have also been set in
accordance with those times...thus giving a correct 12 hrs work for a 1 day
task duration. A custom task and custom resource calendar has been configured
for an 8 hour working day, starting at 08:00. However, when applying the
custom task/resource calendar, the task finishes at 12:00 on the following
day. This indicates that a 1 day task duration equates to 12hrs work, even
though a custom calendar's working day has been defined at 08:00-17:00. This
all seems to come-about because you can define only one set of Hrs-per-day
(in TOC).
The Question: Is it possible to configure the calendars such that, when you
apply a custom resource/task calendar, the default task duration of 1 day is
read in accordance with the working-times specified by the custom
calendar....thus also applying the correct number of working hours?
Have I missed something; is this an "operating characteristic", or do I have
to trick MSP into doing what I would like it to do?
Thanks for any tips or guidance.
James. G
I've been using MSP for several years now (currently on MSP 200)...and I
hope that I'll explain my predicament succinctly
I can set-up the calendars, Change Working Time, and custom calendars
without too much difficulty....and I fully understand (I think!) the settings
via Tools/Options/Calendar (TOC)..which sets the definition of how many hours
equals one working day.
The Problem: If I apply a custom task or resource calendar to that task,
then the start of the task amends in accordance with the custom calendar
(good!), but the duration (therefore the end-date) alters in accordance with
how many hours-per-day have been defined in the TOC settings, regardless of
the working-times set by the custom calendar. This results in an incorrect
number of hours work for the resource, unless I go into each task and amend
the work in accordance with the true working times of the resource.
The Example: The basic/project calendar has been set for 06:00 start: and
18:00 finish, with 12 Hrs-per-day. The basic resources have also been set in
accordance with those times...thus giving a correct 12 hrs work for a 1 day
task duration. A custom task and custom resource calendar has been configured
for an 8 hour working day, starting at 08:00. However, when applying the
custom task/resource calendar, the task finishes at 12:00 on the following
day. This indicates that a 1 day task duration equates to 12hrs work, even
though a custom calendar's working day has been defined at 08:00-17:00. This
all seems to come-about because you can define only one set of Hrs-per-day
(in TOC).
The Question: Is it possible to configure the calendars such that, when you
apply a custom resource/task calendar, the default task duration of 1 day is
read in accordance with the working-times specified by the custom
calendar....thus also applying the correct number of working hours?
Have I missed something; is this an "operating characteristic", or do I have
to trick MSP into doing what I would like it to do?
Thanks for any tips or guidance.
James. G