M
Mike
I'm trying to use a task-level custom cost field and I can not seem to
get it to roll up. It was created in Project Server 2007 as a Task
Entity, Cost Type, Rollup(sum). I have a cost resource assigned to
one of my summary tasks and I exposed my custom Cost field on the Task
Usage view along with the built-in "Cost" column. If I enter a value
into my custom Cost field, it does not rollup. If I enter into the
built-in "Cost" column, it rolls up exactly the way I want. However,
we cannot use the "Cost" field because of it's depencency on
"Remaining Cost" and "Actual Cost." I have tried the "Calculate Now"
button on Tools > Options > Calculation to no availl.
Here are our requirements for this issue:
- Need to use Cost Resources.
- Need to assign the cost resources at the summary task (customer
requirement)
- Need to enter cost in a custom field.
- Need the total cost to roll up at all levels and within groups in
custom views.
Is this by design or is this workable?
Best Regards,
-- Mike
get it to roll up. It was created in Project Server 2007 as a Task
Entity, Cost Type, Rollup(sum). I have a cost resource assigned to
one of my summary tasks and I exposed my custom Cost field on the Task
Usage view along with the built-in "Cost" column. If I enter a value
into my custom Cost field, it does not rollup. If I enter into the
built-in "Cost" column, it rolls up exactly the way I want. However,
we cannot use the "Cost" field because of it's depencency on
"Remaining Cost" and "Actual Cost." I have tried the "Calculate Now"
button on Tools > Options > Calculation to no availl.
Here are our requirements for this issue:
- Need to use Cost Resources.
- Need to assign the cost resources at the summary task (customer
requirement)
- Need to enter cost in a custom field.
- Need the total cost to roll up at all levels and within groups in
custom views.
Is this by design or is this workable?
Best Regards,
-- Mike