S
sjk1000
Hi all
I want to add a custom date field in a new column to show a deadlin
date for reviewing documents - this review period is not a task I wan
to show in the plan.
The review deadline for each document should be equal to the Finis
Date + 2 working days. I can get the "Finish Date + 2" to work but ho
do I specify the calendar the formula needs to use?
Thanks, Stev
I want to add a custom date field in a new column to show a deadlin
date for reviewing documents - this review period is not a task I wan
to show in the plan.
The review deadline for each document should be equal to the Finis
Date + 2 working days. I can get the "Finish Date + 2" to work but ho
do I specify the calendar the formula needs to use?
Thanks, Stev