I want to create a custom enterprise field, and can go through and do this,
but when I try to save my enterprise Global project it tells me that my
resource global (resglobal) project is already checked out...
am i doing something wrong?? I can load up the resglobal project and change
and save this, so checkout cannot be possible can it??
any pointers greatfully received