G
Girija
Hello,
I am using MSP 2003. I want to count the total number of tasks in a project,
so I have used Custom Enterprise Field at Task level with the following
formula
IIf([Summary]=No And [External Task]=No,1,0)
It is working fine. But the same when I did with Custom Enterprise Field at
PROJECT level. It didnt work. Can anyone tell as why it didnt work. Is it by
any way linked to Non availability of Summary and External Link fields?
Thanks
Girija
I am using MSP 2003. I want to count the total number of tasks in a project,
so I have used Custom Enterprise Field at Task level with the following
formula
IIf([Summary]=No And [External Task]=No,1,0)
It is working fine. But the same when I did with Custom Enterprise Field at
PROJECT level. It didnt work. Can anyone tell as why it didnt work. Is it by
any way linked to Non availability of Summary and External Link fields?
Thanks
Girija