Custom Field Calculation

A

Adam Bennett

Hi All
We're on PS2003 and I've created a view in Project Center to show us various
project schedule and budget health metrics. I created a Custom Enterprise
Project Text Field to calculate the Estimate To Complete (ETC) of the project
using the formula "[EAC]-[Actual Cost]". However, after setting this up and
adding the field to the view, it only seems to calculate this for a handful
of the projects we have in the system. There doesn't seem to be any
differentiation between the projects that calculate ETC correctly and those
that don't. They both have a valid EAC and Actual Cost value.

Any ideas on why? Should I be using a Custom Enterprise Project Cost field
instead of the Text field?

Any suggestions would be greatly appreciated.

Thanks!
~Adam
 
M

Marc Soester [MVP]

Hi Adam,

In order to make it visible for all projects you will need to open the
project press F9 ( recalculation ) save and publish the projects. Then all
calcualted values should appear.
hope this helps
 
A

Adam Bennett

Perfect. Thanks for the tip.

Marc Soester said:
Hi Adam,

In order to make it visible for all projects you will need to open the
project press F9 ( recalculation ) save and publish the projects. Then all
calcualted values should appear.
hope this helps
--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com


Adam Bennett said:
Hi All
We're on PS2003 and I've created a view in Project Center to show us various
project schedule and budget health metrics. I created a Custom Enterprise
Project Text Field to calculate the Estimate To Complete (ETC) of the project
using the formula "[EAC]-[Actual Cost]". However, after setting this up and
adding the field to the view, it only seems to calculate this for a handful
of the projects we have in the system. There doesn't seem to be any
differentiation between the projects that calculate ETC correctly and those
that don't. They both have a valid EAC and Actual Cost value.

Any ideas on why? Should I be using a Custom Enterprise Project Cost field
instead of the Text field?

Any suggestions would be greatly appreciated.

Thanks!
~Adam
 