Adam Bennett
Hi All
We're on PS2003 and I've created a view in Project Center to show us various
project schedule and budget health metrics. I created a Custom Enterprise
Project Text Field to calculate the Estimate To Complete (ETC) of the project
using the formula "[EAC]-[Actual Cost]". However, after setting this up and
adding the field to the view, it only seems to calculate this for a handful
of the projects we have in the system. There doesn't seem to be any
differentiation between the projects that calculate ETC correctly and those
that don't. They both have a valid EAC and Actual Cost value.
Any ideas on why? Should I be using a Custom Enterprise Project Cost field
instead of the Text field?
Any suggestions would be greatly appreciated.
Thanks!
~Adam
We're on PS2003 and I've created a view in Project Center to show us various
project schedule and budget health metrics. I created a Custom Enterprise
Project Text Field to calculate the Estimate To Complete (ETC) of the project
using the formula "[EAC]-[Actual Cost]". However, after setting this up and
adding the field to the view, it only seems to calculate this for a handful
of the projects we have in the system. There doesn't seem to be any
differentiation between the projects that calculate ETC correctly and those
that don't. They both have a valid EAC and Actual Cost value.
Any ideas on why? Should I be using a Custom Enterprise Project Cost field
instead of the Text field?
Any suggestions would be greatly appreciated.
Thanks!
~Adam