Custom Field-Finish Variance

R

Rhonda H.

I am trying to set the Graphical Indicator in Custom
Field. I want to use the Finish Variance field for
looking at schedule variances and I want to use graphics
when the "Finish Variance" is within a certain number of
days.
Using Enterprise Custom Field, I selected Enterprise
Number1 (renamed it to Schedule Variance), and then in the
fomula area I selected the field "Finish Variance" with no
other info. When I display the Schedule Variance the
number is no longer in days. For explain the "Finish
Variance" field will show 1 day variance and the "Schedule
Variance" shows 480. They should match.

Does anyone know if there is some calculation that I need
to do? Or, is there some other way to use the Graphical
Indicator without using the Custom Field option?
Thanks in advance.
 
D

Dale Howard

Rhonda --

It's not so hard. The information you lack is that all time values are
stored in Microsoft Project as minutes. So, the 1 day of Finish Variance is
actually 480 minutes of variance. Your formula needs to convert from
minutes to days. You can do so by writing the formula as [Finish
Variance]/480. This assumes that your Hours Per Day value is 8 (this is set
by clicking Tools - Options - Calendar). Hope this helps.
 
D

Dale Howard

Jack -

Good comment. Thanks for the additional thought!

--
Dale A. Howard
Project Management Trainer/Consultant
Denver, CO


Jack D. said:
Note that you can use [Minutes per day] or [Minutes per week] to convert.
This will take into account the cases where a day/ week is defined as
anything other than 8 hours/40 hours. It is good practice to use it instead
of dividing by 480.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP



Dale said:
Rhonda --

It's not so hard. The information you lack is that all time values are
stored in Microsoft Project as minutes. So, the 1 day of Finish Variance
is actually 480 minutes of variance. Your formula needs to convert from
minutes to days. You can do so by writing the formula as [Finish
Variance]/480. This assumes that your Hours Per Day value is 8 (this is
set by clicking Tools - Options - Calendar). Hope this helps.


Rhonda H. said:
I am trying to set the Graphical Indicator in Custom
Field. I want to use the Finish Variance field for
looking at schedule variances and I want to use graphics
when the "Finish Variance" is within a certain number of
days.
Using Enterprise Custom Field, I selected Enterprise
Number1 (renamed it to Schedule Variance), and then in the
fomula area I selected the field "Finish Variance" with no
other info. When I display the Schedule Variance the
number is no longer in days. For explain the "Finish
Variance" field will show 1 day variance and the "Schedule
Variance" shows 480. They should match.

Does anyone know if there is some calculation that I need
to do? Or, is there some other way to use the Graphical
Indicator without using the Custom Field option?
Thanks in advance.



+++++++++++++++++++
 