D
Darrell
All,
In my schedules I have generic resources with the prefix "zz". Project
Managers and Resource Managers are supposed to replace these generics with
named resources prior to 6 weeks from the current date so that from the
current date out 6 weeks we have only named resources. One of the metrics we
are using to review schedule maintenance is the number of generic work hours
within this 6 week window.
So, my question is can I use a custom field to write a formula to copy the
work totals to a number field (done) AND roll up the numbers for just the
tasks with a resources containing the prefix "zz" to the summary tasks using
the same formula?
Darrell
In my schedules I have generic resources with the prefix "zz". Project
Managers and Resource Managers are supposed to replace these generics with
named resources prior to 6 weeks from the current date so that from the
current date out 6 weeks we have only named resources. One of the metrics we
are using to review schedule maintenance is the number of generic work hours
within this 6 week window.
So, my question is can I use a custom field to write a formula to copy the
work totals to a number field (done) AND roll up the numbers for just the
tasks with a resources containing the prefix "zz" to the summary tasks using
the same formula?
Darrell