A
Astro Boy
Hi all,
I desperately need some help writing a formula for a Custom Project
Date Field in my Project Server 2003 installation. Here are the
specifics:
Background:
We have a task, which appears in all of our project schedules, called
"Implementation". This task will appear in a different spot in each
schedule (but only once per schedule), due to differences between the
activities required in each project, so the line number of the task is
not constant. The name of the task, however, is constant. Some
characteristics of the "Implementation" task: It is not a milestone, it
has a duration (typically a day), resources assigned, and work
assigned. We assign a Deadline to the "Implementation" task rather than
a constrained Finish.
What I'm trying to do:
I want to take the Deadline date from the "Implementation" field and
display it on Project Center views. So, I'd like to get the date from
the task-level Deadline into Enterprise Project Date2. If there is no
Deadline date, I'd like to display "NA" or something like it in
Enterprise Project Date2.
What does my formula look like? I'm sure this is simple, but I'm really
struggling with it.
Also, I know the easiest way to do this would be to have the PM
manually enter the date into Enterprise Project Date2, but there are
reasons why this is not a viable solution (extreme reluctance to double
enter anything being one of the reasons).
Thanks in advance for any help you can provide!
AB
I desperately need some help writing a formula for a Custom Project
Date Field in my Project Server 2003 installation. Here are the
specifics:
Background:
We have a task, which appears in all of our project schedules, called
"Implementation". This task will appear in a different spot in each
schedule (but only once per schedule), due to differences between the
activities required in each project, so the line number of the task is
not constant. The name of the task, however, is constant. Some
characteristics of the "Implementation" task: It is not a milestone, it
has a duration (typically a day), resources assigned, and work
assigned. We assign a Deadline to the "Implementation" task rather than
a constrained Finish.
What I'm trying to do:
I want to take the Deadline date from the "Implementation" field and
display it on Project Center views. So, I'd like to get the date from
the task-level Deadline into Enterprise Project Date2. If there is no
Deadline date, I'd like to display "NA" or something like it in
Enterprise Project Date2.
What does my formula look like? I'm sure this is simple, but I'm really
struggling with it.
Also, I know the easiest way to do this would be to have the PM
manually enter the date into Enterprise Project Date2, but there are
reasons why this is not a viable solution (extreme reluctance to double
enter anything being one of the reasons).
Thanks in advance for any help you can provide!
AB