J
John
I have a Cost field (Cost1) that I would like to be a percentage of the
Fixed Cost for a specific task. How do I specify the WBS Fixed Cost field
that I want to use?
Example
WBS1 Fixed Cost = $10,000
WBS2 Cost1 = WBS1.FixedCost * 20%
Thanks
John
Fixed Cost for a specific task. How do I specify the WBS Fixed Cost field
that I want to use?
Example
WBS1 Fixed Cost = $10,000
WBS2 Cost1 = WBS1.FixedCost * 20%
Thanks
John