S
Steve
I'm trying to figure out the correct formula to use with custom fields so
that I can calculate an internal resource cost per task, based on the work
assigned for that task.
For example, my resource is set up with a standard rate of $100 p/h. I have
an internal cost of $50 p/h which means my margin every hour is $50. I have
created a custom Internal Cost field [Cost1] within the resource sheet at $50
and have now created a second custom field [Cost2] called internal cost per
task.
The internal cost per task field uses the formula [Cost1]*[Work]
Whilst testing I have set the work at 10 hours for the task which means that
my resource cost should be $500 but [Cost2] calculated field is returning
$30,000 ???!?!
Can anyone shed light on why this is happening?
that I can calculate an internal resource cost per task, based on the work
assigned for that task.
For example, my resource is set up with a standard rate of $100 p/h. I have
an internal cost of $50 p/h which means my margin every hour is $50. I have
created a custom Internal Cost field [Cost1] within the resource sheet at $50
and have now created a second custom field [Cost2] called internal cost per
task.
The internal cost per task field uses the formula [Cost1]*[Work]
Whilst testing I have set the work at 10 hours for the task which means that
my resource cost should be $500 but [Cost2] calculated field is returning
$30,000 ???!?!
Can anyone shed light on why this is happening?