Custom field from Proj Pro not passing to Project Server 2003

D

Diane

I have added Text1 Custom Field in Tasks in Project Professional. I have
made the field a drop down list for users to choose from.

I have applied Service Pack 1 to Project Server, Database & SharePoint.

Upon saving the project in Project Professional, data is sent to Project
Server EXCEPT Text1. Doesn't this data get transmitted as well, or is there
something I need to do for it to be sent along with the project?

Please help.
Thanks
diane
 
J

Jan Pochobradský

Try use field "Organization-text1" in Task and setup this field as publish.
Jan
 
J

Jonathan Sofer - MCP

Hi Diane,

If you are trying to get the Tex1 data to show in the timesheet view with
data, I believe you will have to add the column to the published fields
section for every project. Go to Tools>Customize>Published fields and move
Text1 to the right. There are some other options to check or uncheck after
you move the column.
 