Custom field indicators

B

Bryan A

How do I use text instead of the graphical indicators in custom fields? I
did something like this but it didn't work.
IIf([Finish Variance]<0,"Ahead of Schedule",IIf([Finish
Variance]>0,"Late","On Schedule"))
Any ideas?

Thanks,
Bryan
 
B

Bryan A

I had it in a number field. Thanks


Dale Howard said:
Bryan --

Did you create this formula in a custom Text field? If not, and you created
it in any type of number field, it will generate an error. Hope this helps.

--
Dale A. Howard
Project Management Trainer/Consultant
Denver, CO


Bryan A said:
How do I use text instead of the graphical indicators in custom fields? I
did something like this but it didn't work.
IIf([Finish Variance]<0,"Ahead of Schedule",IIf([Finish
Variance]>0,"Late","On Schedule"))
Any ideas?

Thanks,
Bryan
 