Custom fields and/or outline codes in Activity Plans?

A

anovaktx

Can an Activity Plan have custom fields or outline codes?

Can the tasks themselves underneath the Activity Plans have custom
fields or outline codes?

This would be in order to ensure the production support work was
grouped along with "projects" to the correct performing group /
manager and be able to rollup to the executive or Director level.

I realize that there is an "owner" of the Activity Plan but wasn't
sure how that would let you group items in reports.

Thanks,
Andy
 
B

Ben Howard

Hi Andy,
There is no way to assign a task custom field within an Activity Plan.

You can only assign custom fields at the project level, so you could create
a specific field to designate APs verses "normal" projects.
 