B
Barb PMO
My company uses Project Pro 2003 and Project Server
I've added 2 Enterprise custom fields, Enterprise Project Cost1 (for the
Project Sale Price) and a field for a calculated value, Enterprise Project
Cost2 (used to calculate the Price per Hour) The formula is Enterprise
Project Cost2 = [Sale Price] / [Baseline Work].
The problem is I'm getting 2 differernt types of weird results.
1) For a project with a sale price of 138,000.00 and Baseline work of 920h,
my expected results are 150.00. Actual results = 2.5
2) For a project with a sale price of 27,035.00 and Baseline work of
213.33h, my expected results are 127.00. Actual results = 211.21
I don't use multiple baselines, and all project sale prices are entered in
Project information as (ex. 138,000.00)
Any ideas?
I've added 2 Enterprise custom fields, Enterprise Project Cost1 (for the
Project Sale Price) and a field for a calculated value, Enterprise Project
Cost2 (used to calculate the Price per Hour) The formula is Enterprise
Project Cost2 = [Sale Price] / [Baseline Work].
The problem is I'm getting 2 differernt types of weird results.
1) For a project with a sale price of 138,000.00 and Baseline work of 920h,
my expected results are 150.00. Actual results = 2.5
2) For a project with a sale price of 27,035.00 and Baseline work of
213.33h, my expected results are 127.00. Actual results = 211.21
I don't use multiple baselines, and all project sale prices are entered in
Project information as (ex. 138,000.00)
Any ideas?