Custom Fields - Time

R

Robin Roe

Hi

I would like a way of being about to store custom inputs broken down into
time periods. This would be similar to say the Actual Work view where values
can be entered for a particular time period.

At the moment we are not using the timesheets to update progress, but is
manually updated by the PM. We already fill in Timesheets on our financial
system, so I was hoping to be able to transfer over these hours into a custom
field. I have looked at putting them into the Actual work field, but this
won’t work as it will only be the very top level tasks that will map from
system to system, so it’s only at that level that I want to bring the hours
across.

Any suggestions at all would be very helpful.
 
D

Dale Howard [MVP]

Robin --

Project Server 2003 automatically saves timephased information for all
default fields related to Cost and Work (Cost, Actual Cost, Baseline Cost,
etc.). I do not believe there is any way to save timephased information in
a custom field, however. Sorry.
 