D
donkeyboy
I'm a newbie with MS Project, and have just started to use custom
fields today, as it looks like they meet a need of mine: I'm trying to
calculate the duration and cost of each project task, if each project
task took 50% longer than initially estimated -- I'm trying to factor
in contingency into the project, and our working practice is to add on
a 1/2.
As such, I'm trying to multiply the duration, work, start and finish
fields all by 1.5, to get the desired result, but I'm ending up getting
error messages, presumably due to syntax mistakes. I've just stumbled
across functions, but without any examples in the help file, I'm
struggling to see what I need to enter in the formulas.
Does anyone have any suggestions on how I can achieve the above?
Thanks in advance.
Ron
fields today, as it looks like they meet a need of mine: I'm trying to
calculate the duration and cost of each project task, if each project
task took 50% longer than initially estimated -- I'm trying to factor
in contingency into the project, and our working practice is to add on
a 1/2.
As such, I'm trying to multiply the duration, work, start and finish
fields all by 1.5, to get the desired result, but I'm ending up getting
error messages, presumably due to syntax mistakes. I've just stumbled
across functions, but without any examples in the help file, I'm
struggling to see what I need to enter in the formulas.
Does anyone have any suggestions on how I can achieve the above?
Thanks in advance.
Ron