C
charlesdlm
Hi,
Really hoping someone can help me with this because I have been lookin
for answer without any success so far.
I have a large project where all my task dependancies are finish
start. (Obviously some tasks have no dependacies at all).
I want to see what tasks my project resources can work on _presently_
This does not necessarily = all open tasks as I dont want to see task
which they cant work on due to the fact that there are relate
predecessors/dependancies still open.
To summarise I would like to see (using a filter)
1. All open tasks without any predecessors &
2. All open tasks with related predecessors/dependancies that ar
themselves completed. Ie if task 5 as a predecessor of task 4 (finis
start) and task 4 is 100% completed then I would like to see task 5. Bu
if task 4 has only 80% then I dont want to see task 5 (as task 5 cant b
started yet).
Eagerly awaiting your responses - Regards Charle
Really hoping someone can help me with this because I have been lookin
for answer without any success so far.
I have a large project where all my task dependancies are finish
start. (Obviously some tasks have no dependacies at all).
I want to see what tasks my project resources can work on _presently_
This does not necessarily = all open tasks as I dont want to see task
which they cant work on due to the fact that there are relate
predecessors/dependancies still open.
To summarise I would like to see (using a filter)
1. All open tasks without any predecessors &
2. All open tasks with related predecessors/dependancies that ar
themselves completed. Ie if task 5 as a predecessor of task 4 (finis
start) and task 4 is 100% completed then I would like to see task 5. Bu
if task 4 has only 80% then I dont want to see task 5 (as task 5 cant b
started yet).
Eagerly awaiting your responses - Regards Charle