Using MSP2003ent

There is a custom filter in Project Pro called (Date Range) which can be
selected and works just as needed, how can I incorporate this filter into the
PWA environment? I have a custom view created in PWA; Type-Project,
Table-Task, but don't see Date Range listed under Filter section.
 
S

Sean Hanson

This is the same as applying the Custom Filter on your Start Dates, select
custom filter and Start for Field Name, Test = is greater than and the value
you want then AND Finish for Field Name, Test = is less than and the falue
you want on your Finish dates. No it is not like in Pro, but it does exactly
the same thing.
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool