J
Jason
I'm trying to develop a custom formula for late tasks, but have little
expereince in this area. I need on sched, behind sched, and over 2 weeks
sched. I believe what I can't fingure out is the over 2 weeks piece
(calculation).
IIf((([Task Baselined?]="Baselined") And ([Baseline Finish]<[Finish])),"Task
Behind Schedule",IIf((([Task Baselined?]="Baselined") And ([Baseline
Finish]=[Finish])),"Task On Schedule",IIf((([Task Baselined?]="Baselined")
And ([Baseline Finish]<[Finish])),"Over Two Weeks",IIf([Task Baselined?]="No
Baseline","Task Not Baselined","Calculation Error"))))
Jas
expereince in this area. I need on sched, behind sched, and over 2 weeks
sched. I believe what I can't fingure out is the over 2 weeks piece
(calculation).
IIf((([Task Baselined?]="Baselined") And ([Baseline Finish]<[Finish])),"Task
Behind Schedule",IIf((([Task Baselined?]="Baselined") And ([Baseline
Finish]=[Finish])),"Task On Schedule",IIf((([Task Baselined?]="Baselined")
And ([Baseline Finish]<[Finish])),"Over Two Weeks",IIf([Task Baselined?]="No
Baseline","Task Not Baselined","Calculation Error"))))
Jas