Hello Fellow P2K2 Users,

Is there a way to create a custom Gantt view that will
show more than the original baseline? I would like to
have a graphic bar that shows Baseline1 or Baseline2 and
can't figure out a way to do it. I'd appreciate any info
I can get on this issue.

Thanks,
Debbie
 
J

jb

Open the Tracking Gantt view.
Select [Format][Bar Styles]
Click on the Baseline row
Click [Cut Row][Paster Row][Paste Row]
On the First Baseline line:
Change the Name from "Baseline" to "Baseline1"
Change the color if desired
Change the Row # if desired
Change the From to "Baseline1 Start"
Cange the To field to "Baseline1 Finish"
Click OK
 
M

Mike Glen

Hi Debbie,

Welcome to this Microsoft Project newsgroup :)

Although written for Project 98, the principles are the same - please see
FAQ Item: 14. Viewing Multiple Baselines. FAQs, companion products and
other useful Project information can be seen at this web address:
http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen