- Joined
- May 25, 2016
- Messages
- 2
- Reaction score
- 0
We are using Project Server Online. I am working on sending our PWA time to our internal TimeTracking system. One field called TimeTrack Activity (TT Activity) is required for each timesheet line to indicate what the person was doing. For instance a TT Activity can be Testing, Deliver-Implement, Rework, etc. The resource needs to choose the appropriate TT Activity when entering time.
I added a TT Activity as a TASK field in PWA and set Deliver-Implement as the default. I also added this field to the MY Timesheet view and unchecked “Make Field Read Only” to allow the user to change the value in My Timesheet. So now I can go to My Timesheet, enter time and also change TT Activity for instance to Rework. I can log out and come back in. My change of TT Activity remains as Rework.
I then tried to pull my time with TT Activity using Power Query going against oData. I cannot find TT Activity as a field to choose. Is there a way to add the field into my Power Query?
Thanks
John
I added a TT Activity as a TASK field in PWA and set Deliver-Implement as the default. I also added this field to the MY Timesheet view and unchecked “Make Field Read Only” to allow the user to change the value in My Timesheet. So now I can go to My Timesheet, enter time and also change TT Activity for instance to Rework. I can log out and come back in. My change of TT Activity remains as Rework.
I then tried to pull my time with TT Activity using Power Query going against oData. I cannot find TT Activity as a field to choose. Is there a way to add the field into my Power Query?
Thanks
John