Hi Dan
I find the Resource Usage view printed to a Pdf file
pretty handy for this. You will need a pdf writer if you
want to distribute soft copy.
Insert a column for Project, and if the file is open its
name will be shown. Otherwise it shows the path of the
project.
Where I have many work items included in one an overall
project, I enforce prefixing the taskname with the work#
in the planning templates. Works well.
Email me and I will send an example.

Regards.........Geoff
 