K
Ken
One of our departments has been using a pair of custom task forms to keep the
group organised. They worked within the limitations to send the tasks from a
centralised mailbox and so far everything has worked very well.
Then I went and upgraded our Exchange server from 5.5 to 2003 (swing) and
now these tasks are giving us grief. If the administrator sends out multiple
tasks to a person, as soon as the recipient accepts one, all of them get
moved into the trash. Viewed in the message list, the subject line displayed
each is unique, but when opened, each task is identical including the subject.
I have been to Sue's site and am aware of the cautions against custom tasks,
but these were working just fine on the old server. Is there something
different in how the 2003 server is handling these tasks?
We are still using Outlook 2000 to access the server right now, though I do
plan to test the task behaviour with Outlook 2003 since we're planning to
upgrade anyway.
Thanks in advance,
Ken
I kept a few aside myself and have determined that the message id is unique
for each task and they open up with the custom form properly.
group organised. They worked within the limitations to send the tasks from a
centralised mailbox and so far everything has worked very well.
Then I went and upgraded our Exchange server from 5.5 to 2003 (swing) and
now these tasks are giving us grief. If the administrator sends out multiple
tasks to a person, as soon as the recipient accepts one, all of them get
moved into the trash. Viewed in the message list, the subject line displayed
each is unique, but when opened, each task is identical including the subject.
I have been to Sue's site and am aware of the cautions against custom tasks,
but these were working just fine on the old server. Is there something
different in how the 2003 server is handling these tasks?
We are still using Outlook 2000 to access the server right now, though I do
plan to test the task behaviour with Outlook 2003 since we're planning to
upgrade anyway.
Thanks in advance,
Ken
I kept a few aside myself and have determined that the message id is unique
for each task and they open up with the custom form properly.