Custom View Creation

H

Haris

Hi,
I'm trying to create a custom Project view in PWA. I need to show 3 fields,
out of which 2 are enterprise Resource Fields and 1 is Enterprise Task field.
But in the view, i can either add a Task field or a Resource Field but not
both.
I need a number based field to show the threshold value defined by PM for
each task. Then i want to group this view by Resource Group field such that i
can see each resource's work separated by their role, even when there are 2
resources, having different roles, assigned to a single task, i see them in
two different rows/groups. Any ideas how to accomplish this?
Looking forward.

Regards,
Haris
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top