I am running proj 2002 std. I have created a custom
resource sheet view. I created this for a resource pool
and want to incorporate this view, which contains custom
fields....text and flag fields.....across all my resource
pools. I have gone to tools....organizer....and copied
the resource entry table, resource sheet view, and the
custom fields to the global.mpt. However, when I open
another project, I have the default resource sheet view.
What am I missing? Any comments suggestions welcome.
 
J

JulieS

Hi Cheryl,
When you copied the custom features to the global.mpt
file, those changes would only be reflected in *new*
projects.
Open the file you need the custom features in, and then
copy the features from the global.mpt file to the other
file. (You may also copy directly from one file to
another file as long as both files are open.)
Hope this helps.
Julie
 