Custom View

M

Muks

I want to create a custom view in which fields from Gnatt Chart (Text 1) and
Resource Usage (Text 1) be selected. Is there any way I would be able to get
this?

Appreciate suggestions.

MM
 
M

Mike Glen

Hi MM,

Welcome to this Microsoft Project newsgroup :)

There's a macro on offer to transfer data from one to the other. So you
could, say, pick the Gantt Chart view, create a copy of the Entry table, and
use an empty Text field to copy from the Text1 resource field. Then use
that new table for your custom view. The macro is in FAQ Item: 37 - Custom
Fields in Tables. FAQs, companion products and other useful Project
information can be seen at this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
..
 