G
geoff.pratt
I have created a custonised field with custom formulas and
using the Graphical Indicators table to indicate task
status (Red/ Yellow/ Green) in terms of schedule status.
This works fine at the task level. However, at the summary
level it is unpredictable.
The summary task view is the view I would prefer to
distribute, as I have many inserted projects and master
plan views.
The only way I can get the summary result to show the
correct status is to key the code number into the field
manually.
Is there a way for the summary task to be subjected to the
same test as at task level??
Would appreciate your advice.
Geoff
using the Graphical Indicators table to indicate task
status (Red/ Yellow/ Green) in terms of schedule status.
This works fine at the task level. However, at the summary
level it is unpredictable.
The summary task view is the view I would prefer to
distribute, as I have many inserted projects and master
plan views.
The only way I can get the summary result to show the
correct status is to key the code number into the field
manually.
Is there a way for the summary task to be subjected to the
same test as at task level??
Would appreciate your advice.
Geoff