Customised Fields and Summary Tasks

G

geoff.pratt

I have created a custonised field with custom formulas and
using the Graphical Indicators table to indicate task
status (Red/ Yellow/ Green) in terms of schedule status.
This works fine at the task level. However, at the summary
level it is unpredictable.
The summary task view is the view I would prefer to
distribute, as I have many inserted projects and master
plan views.
The only way I can get the summary result to show the
correct status is to key the code number into the field
manually.
Is there a way for the summary task to be subjected to the
same test as at task level??
Would appreciate your advice.

Geoff
 
J

JackD

Go to the customize fields dialog box (same place you entered the formula
and set the indicators)
Make sure that the summary task is using the formula to calculate.

-Jack
 
G

geoff.pratt

Thanks Jack,
Works a treat.

Geoff
-----Original Message-----
Go to the customize fields dialog box (same place you entered the formula
and set the indicators)
Make sure that the summary task is using the formula to calculate.



.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top