Customising Fields

S

Sara

Hi,
I am trying to produce new columns that will force the entered data (and
summed tasks) to show in Hours. I know 'Work' does this but I need more than
one column and if I select any of the Duration fields the data defaults to
Days.

Please help!!

Thanks,
Sara
 
J

JulieS

Hello Sara,

You can show the custom Duration field in another field formatted as
you'd like. Unfortunately you cannot apply the formatting directly
to the field you are entering the data into, but it may suit your
needs.

If you are entering your data into Duration1 field - add Duration2
and create the following formula in Duration2:

ProjDurConv([Duration1],pjHours)

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

John

Sara said:
Hi,
I am trying to produce new columns that will force the entered data (and
summed tasks) to show in Hours. I know 'Work' does this but I need more than
one column and if I select any of the Duration fields the data defaults to
Days.

Please help!!

Thanks,
Sara

Sara,
Remember, the Work fields and Duration fields are completely different
and the default dimension for each is set under Tools/Options/Schedule
tab.

John
Project MVP
 
M

Mike Glen

You also have the option uner Tools/Macro/Macros... to select the
Format_Duration macro which will set all Durations to the option selected.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top