Is there any way to customize the task reminder emails in Project? When a
user receives a Task reminder from the Microsoft Office Project Server 2007
notification service, the format is so:
The following tasks for your resources are currently overdue.
Project: Clinic
Assigned to: John Black
Task Name: Install
Start: Thursday, September 27, 2007 Finish: Thursday, September 27, 2007
Work: 2h Remaining Work: 2h % Completion: 0
Project: Clinic
Assigned to: John Black
Task Name: Data Import
Start: Thursday, September 27, 2007 Finish: Thursday, September 27, 2007
Work: 2h Remaining Work: 2h % Completion: 0
We would like additional information added, such as the Upper Level task's
name.
Is there a config file somewhere on the Project Server that I could edit to
achieve this?
user receives a Task reminder from the Microsoft Office Project Server 2007
notification service, the format is so:
The following tasks for your resources are currently overdue.
Project: Clinic
Assigned to: John Black
Task Name: Install
Start: Thursday, September 27, 2007 Finish: Thursday, September 27, 2007
Work: 2h Remaining Work: 2h % Completion: 0
Project: Clinic
Assigned to: John Black
Task Name: Data Import
Start: Thursday, September 27, 2007 Finish: Thursday, September 27, 2007
Work: 2h Remaining Work: 2h % Completion: 0
We would like additional information added, such as the Upper Level task's
name.
Is there a config file somewhere on the Project Server that I could edit to
achieve this?