K
KLA
I am attempting to customize the finish 1 field. I want the value to be
calculated based on the Actual Start date + 40 days duration (which I have
used duration 1, populated with 40d) based on my project calendar. This
formula works and gives the value that I expected however if the Actual Start
date has not yet been populated (tasks that have not yet started) and the
current value is NA I am receiving an error message in the customized finish
1 field. How can I modify my formula to ignore the "NA"'s in the Actual
start column? The following is the current formula:
ProjDateAdd([Actual Start],[Duration1],[Project Calendar])
calculated based on the Actual Start date + 40 days duration (which I have
used duration 1, populated with 40d) based on my project calendar. This
formula works and gives the value that I expected however if the Actual Start
date has not yet been populated (tasks that have not yet started) and the
current value is NA I am receiving an error message in the customized finish
1 field. How can I modify my formula to ignore the "NA"'s in the Actual
start column? The following is the current formula:
ProjDateAdd([Actual Start],[Duration1],[Project Calendar])