H
Herve Zaidman
Hello,
I am trying to create a customized field that will do the following:
-Take today's date minus the finish date of a task then compare the value to
the remaining duration to provide with an estimated status of the task going
to be late or on time (using the added field on the project, I put Green,
Yellow, Red icon to specify which tasks are going to ok, maybe late, are
late). This is mostly for upper management and I am sure that there are other
ways of doing the same thing (I would not mind hearing about it too).
I have used multiple different formulas but it does not seems to come
accross as expected.
Again here is my idea as an example:
Working 8 hours a day/40 hours a week for 4 weeks would be 20days/160 hours
total.
Start date is: 10/01/2007
Finish date is: 10/30/2007
Today's date is: 10/05/2007
The task is at 10% completion (meaning 16 hours would have been spent on
it).
If I were to compare: Finish date - Today's date, I would get (I am
guessing) 16 days left.
Based on it, I would want to then compare the amount of days left (16) to
the Remaining Duration (10% of total 20 days/160 hours would be 2 days/16
hours) and would find that I am in jeopardy already since I should really be
at almost 25%.
Let me know if that makes sense, or need more clarification.
Any input would be appreciated.
Thanks
I am trying to create a customized field that will do the following:
-Take today's date minus the finish date of a task then compare the value to
the remaining duration to provide with an estimated status of the task going
to be late or on time (using the added field on the project, I put Green,
Yellow, Red icon to specify which tasks are going to ok, maybe late, are
late). This is mostly for upper management and I am sure that there are other
ways of doing the same thing (I would not mind hearing about it too).
I have used multiple different formulas but it does not seems to come
accross as expected.
Again here is my idea as an example:
Working 8 hours a day/40 hours a week for 4 weeks would be 20days/160 hours
total.
Start date is: 10/01/2007
Finish date is: 10/30/2007
Today's date is: 10/05/2007
The task is at 10% completion (meaning 16 hours would have been spent on
it).
If I were to compare: Finish date - Today's date, I would get (I am
guessing) 16 days left.
Based on it, I would want to then compare the amount of days left (16) to
the Remaining Duration (10% of total 20 days/160 hours would be 2 days/16
hours) and would find that I am in jeopardy already since I should really be
at almost 25%.
Let me know if that makes sense, or need more clarification.
Any input would be appreciated.
Thanks