T
Thomas
I need a customized field that calculates the following
IIf([Remaining Work]=0;[Baseline Work];0
That is: I need the field 0 as long as Remaining Work is not 0. When Remaing Work is 0 i want the field to be equal to Baseline Work.
I tried this: Entered the above formula in a custom "duration" field - but the field stays 0 no matter what the value of Remaining Work is. Any clue?
IIf([Remaining Work]=0;[Baseline Work];0
That is: I need the field 0 as long as Remaining Work is not 0. When Remaing Work is 0 i want the field to be equal to Baseline Work.
I tried this: Entered the above formula in a custom "duration" field - but the field stays 0 no matter what the value of Remaining Work is. Any clue?