Customizing columns in Approve Timesheets screen

E

etcy

Hi,

I'm administering Project Server / PWA 2003, and my resource managers have a
gripe with the Approve Timesheets screen. When they go there to approve
their resources' timesheets, they can only see the actual work (hours) that
their resources input and submitted.

The resource managers want to see more fields (columns) on that screen,
especially the baseline work for each task. Is there anyway to customize the
Approve Timesheets screen by adding more columns?

I believe this is the TSApp.asp page from the URL.

Thanks!

Regards,
Ed
 
E

etcy

Hi Dale,

Thanks for the response. However I wasn't referring to the (task) Updates
page.

The page I'm referring to is the Approve Timesheets screen accessible under
the Resources tab (or when you click the timesheets pending approval link on
your PWA home page).

For some reason I can't find it on MS help, but if you look at the first
screenshot in
http://office.microsoft.com/en-us/projservadmin/HA011713801033.aspx , on the
left under Actions, there's the Approve Timesheets link, that's the page I'm
referring to.

Hope this clarifies.

Thanks!
Ed
 
D

Dale Howard [MVP]

Ed --

In Project Server 2003, it is not possible to modify the Approve Timesheets
page. Sorry.
 