S
Sundar Ramani
I have given the resource allocation and total effort calculated for each
tasks in MS Project. MS Project automatically calculated duration for all the
tasks. The duration is calculated in terms of days.
Almost all the tasks have the duration in decimals. I require it to display
the whole number in the same column. Is that possible?
I tried including the custom filed of say Duration 1 and tried to round the
values of Duration Field. But i could not get the function(round) in the list
of functions MS Project gives.
Is there any function to display only the whole numbers of the Duration
Field? or is there any other way to resolve this?
Please help me out in this regard.
tasks in MS Project. MS Project automatically calculated duration for all the
tasks. The duration is calculated in terms of days.
Almost all the tasks have the duration in decimals. I require it to display
the whole number in the same column. Is that possible?
I tried including the custom filed of say Duration 1 and tried to round the
values of Duration Field. But i could not get the function(round) in the list
of functions MS Project gives.
Is there any function to display only the whole numbers of the Duration
Field? or is there any other way to resolve this?
Please help me out in this regard.