N
Nitesh
Hi Friends
I’m using Project professional 2003 and need to customize some fields to
calculate Finish Variance & % Finish Variance upto 10, for some analysis
purpose.
The formula which I’m using is:
• Finish Variance 1, Finish Variance 2 to Finish Variance 10– Global Custom
filed to be created w.r.t. the equation (Finish Date – BaselineN Finish Date)
where N=1,2,…10 based on internally baselined information.
• % Finish VarianceN = (Finish VarianceN)/(BaselineN Duration)
Details about fields:
1. Finish Variance1 is Enterprise Number 1 field and same is upto Finish
Variance10 is Enterprise Number 10. And the formula which I have used is same
is mention above.
2. % Finish VarianceN is Enterprise NumberN field.
Problem:
Finish Variance1……..Finish Variance10 shows correct value but %Finish
Variance not display correct value. I think I’m using two different values (
Finish Variance as Number & Baseline Duration as Duration field) or may be
using wrong filed type (Enterprise / Custome fileds) for calculation. May be
I’m wrong but need your help to correct it.
This is required because of doing some analysis by Sr. Management.
I’m using Project professional 2003 and need to customize some fields to
calculate Finish Variance & % Finish Variance upto 10, for some analysis
purpose.
The formula which I’m using is:
• Finish Variance 1, Finish Variance 2 to Finish Variance 10– Global Custom
filed to be created w.r.t. the equation (Finish Date – BaselineN Finish Date)
where N=1,2,…10 based on internally baselined information.
• % Finish VarianceN = (Finish VarianceN)/(BaselineN Duration)
Details about fields:
1. Finish Variance1 is Enterprise Number 1 field and same is upto Finish
Variance10 is Enterprise Number 10. And the formula which I have used is same
is mention above.
2. % Finish VarianceN is Enterprise NumberN field.
Problem:
Finish Variance1……..Finish Variance10 shows correct value but %Finish
Variance not display correct value. I think I’m using two different values (
Finish Variance as Number & Baseline Duration as Duration field) or may be
using wrong filed type (Enterprise / Custome fileds) for calculation. May be
I’m wrong but need your help to correct it.
This is required because of doing some analysis by Sr. Management.