Hi,

could you please advise on the following questions:

1) is it possible to highlight the changes that team member has made for
his tasks (either saved or recalculated)?

2) can I configure the timeframe for Tasks view to be Monday-Sunday, not
the current date +/- 3 as it is by default?

3) can I add to the Task view a custom read-only field?

I think all these tasks can be done only programmatically. But would you
advise on how to perform this?

Thanks in advance,
Elena
 