Customizing the Gantt View on the Project Server

K

katieb018

Hello-

I was wondering if it was possible to create a workplan view on the
Project Server that allowed the viewer to see 2 views simultaneously
and side by side: a Task Usage view on the left side of the screen and
a corresponding Gantt Chart on the right hand side of the screen.
Presently, the Task Usage view lays out the following information: on
the left screen, the task is listed, then all resources assigned to the
task and their corresponding baseline work, actual work and remaining
work, etc. On the right screen the corresponding timesheet view
dispays, allowing the viewer to check details such as actual work,
baseline work, cumulative work, etc for each resource in a given,
modifiable date range.

Is it possible to change that timesheet view on the right to a gantt
chart, that is specific to the tasks and also the resources listed in
the task usage view?

Please let me know if this makes sense and is possible.

Thanks!
KatieB
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top