Customizing the Task Usage View

D

DodoMSP

I currently have a Task Usage View that displays information up to 2049.
My project end date is 2017.

How can I customize the view to only show data up to 2017?
I have a lot of blank on the right side and that make the printout out the
view difficult.

Thanks

DodoMSP
 
R

Rod Gill

Project always fills a printed page, so just double-click the timescale and
increase the zoom so your bars spread across the whole page.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




DodoMSP said:
I currently have a Task Usage View that displays information up to 2049.
My project end date is 2017.

How can I customize the view to only show data up to 2017?
I have a lot of blank on the right side and that make the printout out the
view difficult.

Thanks

DodoMSP

__________ Information from ESET Smart Security, version of virus
signature database 4702 (20091219) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4702 (20091219) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top