Cut off beginning of task

V

Vadim Roulnov

Hello all,

What I need is to cut off beginnig of a task up to date D, where D is
somewhere between t.Start and t.Finish. In other words, the resulting task
should look just like the original one but without its starting part from
the start to D-1. And the resulting task should start on date D. It can be
pictured like this:

O: -------===========--------
R: ------------========--------

How could I do that?

The reason of such a necessity is that we have a number of projects with
_permanent_ tasks. As these projects grow, we want first to archive them and
then cut them down.

Thanks,

-Vadim
 