N
Nikou
Currently, we only have work resources in our project schedules (no material,
budget or fixed cost) and all of our resources (staff) use the same blended
standard rate that we never change. And we don't track cost. Is it correct to
say then our BCWP and ACWP(AC) should be always equal, and have a zero CV all
the time?
I can see that some of our projects show values in fron of SV% and SPI other
that 0% and 1, and I am trying to figure why. (Because our blended standard
rates are not accurate, we can not get accurate values for SV and CV, so we
rae using SV% and CV%, SPI, and CPI measures only).
Thanks for your help!
budget or fixed cost) and all of our resources (staff) use the same blended
standard rate that we never change. And we don't track cost. Is it correct to
say then our BCWP and ACWP(AC) should be always equal, and have a zero CV all
the time?
I can see that some of our projects show values in fron of SV% and SPI other
that 0% and 1, and I am trying to figure why. (Because our blended standard
rates are not accurate, we can not get accurate values for SV and CV, so we
rae using SV% and CV%, SPI, and CPI measures only).
Thanks for your help!