Sorry but it doesn't work that way. Work resource costs are always prorated
to a per hour rate regardless of how they are entered, so a cost of $80 per
day when the resource is assigned to a 1 hour task will impact your budget
by $10, not the $80 you want. This is one of the reasons I harp on the
notion that Project is not an accounting program and shouldn't be kludged in
an attempt to make it play one on TV <g>. The project budget is the direct
economic cost of doing the project's work, NOT the firm's out-of-pocket
expenses. That extra $70 you have to pay him when you're so inefficient as
to use him for only 1 hour is NOT a project related cost - it's overhead to
the firm and should not be included in the project-specific budget costs.
It works the other way as well - overtime work done outside working hours by
an exempt resource who does not earn overtime is not free, even though he
doesn't get paid for the extra time and the out-of-pocket payroll costs
don't increase, the budget still needs to include those hours in the costs
just as if they were worked during regular working time. IMHO, the overtime
rate should equal the standard rate for exempt resources who do not receive
overtime, NOT zero as many references state.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
sorry to not be clear...
I know the difference between them... but what about if I have a fix
cost every day that I usa a specific resource??? (it doesn't matter if
I use for one hour or for the alll day....)
thanks
Vit