daily (or weekly) bases quantities

R

raduga_bf

Hi all,

There are several concrete works for several structures.

Structure 1, Concrete 100 cum, between 1 September and 30 September.
Structure 2, Concrete 50 cum, between 15 September and 25 September.
Structure 3, Concrete 250 cum, between 5 September and 20 September.
etc..

I want to get daily or weekly bases concrete quantity. Exp., on 16
september, how many cum concrete must be placed ?

Is it possible under MSProject ? or I have use some external programs ?

Regards,
 
G

Gérard Ducouret

Hello Raduga,
Quite simple :
In the Resource Sheet, create a resource "Concrete", Type = Material,
Material label = cum
Create a 1 month task (1 month = 20 days on my computer : Tools / Options /
Calendar)
Assign this ressource on the task : units = 100 (cum)
Look at the resource Usage View : the Work or Cumulative work give what you
want.

Hope this helps,

Gérard Ducouret [Project MVP]
 