raduga_bf
Hi all,
There are several concrete works for several structures.
Structure 1, Concrete 100 cum, between 1 September and 30 September.
Structure 2, Concrete 50 cum, between 15 September and 25 September.
Structure 3, Concrete 250 cum, between 5 September and 20 September.
etc..
I want to get daily or weekly bases concrete quantity. Exp., on 16
september, how many cum concrete must be placed ?
Is it possible under MSProject ? or I have use some external programs ?
Regards,
There are several concrete works for several structures.
Structure 1, Concrete 100 cum, between 1 September and 30 September.
Structure 2, Concrete 50 cum, between 15 September and 25 September.
Structure 3, Concrete 250 cum, between 5 September and 20 September.
etc..
I want to get daily or weekly bases concrete quantity. Exp., on 16
september, how many cum concrete must be placed ?
Is it possible under MSProject ? or I have use some external programs ?
Regards,