Dailywise resource allocation

B

binoy4u

HI All,
I am trying to fetch dailywise allocation of resource. Where do I get
no of
unit resource assigned on daily. I am using OLEDB.11(MSP 2003) to
access
values from tables. Assignment table contains only cumulative quantity
of
resource allocated. But in AssignmentTimephasedByDay , i can see
datewise
allocation. But I couldnt get unit assigned dailybasis. Please help me
Thanks in advance